Completion of Krafla Geothermal Power Plant

Gunnlaugur Nielsen, RunÛlfur Maack, ¡sgrÌmur Gudmundsson and Gunnar Ingi Gunnarsson

Key words
volcanic activities, geothermal utilization, power plant, case history, Krafla, Iceland
Location
Krafla, Iceland
Conference
World Geothermal Congress
Year
2000
Session
Power Generation
Language
English
Paper number
R0689

Full text

384, opens in a new tab

Abstract

The preparation for the construction of the 60 MW Krafla Geothermal Power Plant started in 1974. Almost simultaneously volcanic activity started in the region and affected the chemistry of the geothermal fluid. This gave serious problems in the harnessing of the steam and the treatment of the geothermal fluid. Originally two 30 MW units were purchased but the installation of the second unit was postponed until further notice as a result of steam shortage. The volcanic activity ended in 1984 and since then the chemistry of the fluid has improved considerably. In 1996 Landsvirkjun (the National Power Company) decided to complete the installation of unit 2 and to drill for additional steam to reach fully rated power on the plant. The project has been successfully completed and the plant has been running on full load since 1998. The battle of completing the power plant and furnish it with the latest and most modern technology has lasted over a period of 25 years. Although Mother Nature resisted human intervention the battle has been won by Icelandic know-how. The future of the plant is promising and there are good prospects for further extension of the plant.

Copyright 2000, International Geothermal Association. Readers who download papers from this site should honour the copyright of the original authors, and may not copy or distribute the work further without the permission of the original publisher.

Attend the 2029 World Geothermal Congress. Congress details
You have opened 0 records today from 216.73.217.173 (216.73.217.173).
Viewed 22 September 2026, 9:59 pm.