Project Development Update of the Dieng Unit-2 Geothermal Power Plant, Dieng Geothermal Field, Indonesia
- Key words
- project development, drilling campaign, well testing, Dieng Geothermal Field
- Conference
- Stanford Geothermal Workshop
- Year
- 2024
- Session
- Field Studies
- Language
- English
- Paper number
- Alamsyah
Full text
1904 KB, opens in a new tab
Abstract
The Commercial Operation Date (COD) for Dieng Powerplant Unit-1, operated by PT. Geo Dipa Energi (Persero), was in 2002 with installed capacity 1x55 MW. First well for Dieng Unit-1 drilled back in 1975 and ended in 1998. Dieng is a liquid dominated geothermal field with relatively deep and high temperature reservoir. The main reservoir temperature ranges from 300-330oC and located around 500-(-500) mASL. The highly productive reservoir in the Dieng area has been providing two-phase fluids with low non-condensable gas content. Dieng Unit-2 is Dieng Unit-1 expansion, aims to obtain capacity of approximately 55+10% buffer MWe. The development plan will be concentrated in the Sileri area with early estimation of at least 6.2 square-kilometers proven area. The plan has been designed to achieve maximum steam availability, adequate injection capacity, and optimum long-term reservoir performance. The plan includes drilling a total of 10 wells, consist of 5 production wells and 5 injection wells. The last well for Unit-2 is drilled in August 2023, with success ratio 100% target achieved. The drilling campaign result has been extending the proven area to 11.7 square-kilometers.
Copyright 2024, Stanford Geothermal Program. Readers who download papers from this site should honour the copyright of the original authors, and may not copy or distribute the work further without the permission of the original publisher.