Challenges Affecting Procurement Process for Geothermal Projects in Tanzania
- Key words
- Tanzania, geothermal, procurement
- Conference
- World Geothermal Congress
- Year
- 2020
- Session
- Policy, Legal and Regulatory Aspects
- Language
- English
- Paper number
- 03022
Full text
464 KB, opens in a new tab
Abstract
Geothermal development industry is a new venture in Tanzania that involves a number of development stages with multi-procurement processes in almost every stage of development until the project is realized. Tanzania Geothermal Development Company Limited (TGDC) is the sole company (100% owned by the Government) dedicated to spearhead geothermal development in Tanzania. TGDC since it’s establishment has been engaged in different geothermal research projects and other projects for establishment of suitable environment for smoothen and sustainably development of geothermal in the country. Procurement processes have been taking place in almost all the projects implemented. Both Government funds and development partner funds have been used to finance the projects. The first major procurement for geothermal associated activities was registered in 2015 which involved funds from development partner (AfDB) under Scaling up Renewable Energy (SREP) funds. Since then a number of challenges have been recorded e.g. risk management, procurement time, lack of local suppliers, unclear development partners’ conditions, and changing of project implementation guidelines, and managing political expectations. This paper will discuss the challenges encountered in various procurement processes and will pause some mitigation measures taken. Much focus will be on the Ngozi Geothermal Prospect, being the flagship site for Tanzania Geothermal Projects Development.
Copyright 2020, International Geothermal Association. Readers who download papers from this site should honour the copyright of the original authors, and may not copy or distribute the work further without the permission of the original publisher.