Remedial of Geothermal Well: Case Study Sendangan-3, Tompaso Project
- Key words
- casing collapse, Remedial, production well testing, wellbore simulation, Tompaso
- Conference
- World Geothermal Congress
- Year
- 2015
- Session
- Drilling and Completion Technology
- Language
- English
- Paper number
- 21024
Full text
501 KB, opens in a new tab
Abstract
Abstract Well Sendangan-3 has been spud-in since February 2009 and completed on April 2009. This well is a directional well with Big Hole configuration consists of four different types of casing, specifically 20”, 13-3/8” (production casing), 10-3/4” and 8-5/8” (perforated liner). This well is dedicated as production well. Prior to production well testing using Lip Pressure method, the vertical discharge from the well showed a significant decline rate in which indicated a reduction of hole-diameter (production casing collapse). In order to maintain the steam availability at the wellhead, remedial well has been conducted by changing the size of production casing into smaller size. This paper emphasizes on the importance of remedial well by comparing well potency before and after the remedial. This includes the wellbore simulation as if the collapsed casing never existed.
Copyright 2015, International Geothermal Association. Readers who download papers from this site should honour the copyright of the original authors, and may not copy or distribute the work further without the permission of the original publisher.