Conference Papers Database New search

Long Term Use of Acidic Reservoir at Onikobe Geothermal Power Plant.

Abe, M.

Location
Onikobe, Japan
Conference
New Zealand Geothermal Workshop
Year
1993
Session
Theme Papers
Language
English

Full text

709KB, opens in a new tab

Abstract

Onikobe Geothermal Power Plant is a single flash type geothermal plant. It has been operated for 18 years since march 1975. At present, Onikobe Geothermal Power Plant has 9 production wells and 6 reinjection wells. 5 of production wells are used, and the hot water after steam-water separation of three of these wells exhibit acidity which is 3 or a fraction more in values. The steam production from these acid wells accounts for approximately 70%of the total steam. Based on our long experience on the hydrochloric acidic reservoir at Onikobe Geothermal Power Plant, it has been verified that a life of production well more than 8 years can be maintained without using special materials (8 years means the average of a life of production well in Onikobe), if the of hot water is 3.4 or so. The stainless steel material has to be used for the well-mouth equipment down to the separator, but this does not pose an economic problem. It is recommended that the use of acidic reservoir is studied with positive attitude in other geothermal regions.

Copyright 1993, University of Auckland. Readers who download papers from this site should honour the copyright of the original authors, and may not copy or distribute the work further without the permission of the original publisher.

You have opened 0 records today from 216.73.217.167 (216.73.217.167).
Viewed 21 September 2026, 1:25 pm.