Lahendong II Geothermal Power Plant Project in Indonesia
- Key words
- Power Plant; Indonesia, north sulawesi, 20 months project period, 20 MW, series plant
- Location
- Sulawesi; Lahendong, Indonesia
- Conference
- Geothermal Resources Council Transactions
- Year
- 2007
- Session
- Power plant design and operation
- Language
- English
Abstract
The Lahendong II Geothermal Power Plant (LH2), owned by PT. PLN Persero, started commercial operation in June 2007. LH2 is an extension of the Lahendong I Geothermal Power Plant (LH1), and provides 20 MWe additional generating capacity for the public grid. Fuji Electric Systems Co., Ltd. (FES) constructed LH2 as an entirely turnkey project, acting as a subcontractor to Sumitomo Corporation. The turbine-generator units for the plant were manufactured and supplied by FES and the balance of the plant facilities were procured by an internal consortium consisting of FES and PT. Rekayasa Industri. In this paper we describe the principal characteristics of the new LH2 plant.
Copyright 2007, Geothermal Resources Council. Readers who download papers from this site should honour the copyright of the original authors, and may not copy or distribute the work further without the permission of the original publisher.