Well Productivity Enhancement by Drilling Multi-Legged Wells: A Quantitative Assessment

Sanyal, Subir K.; Morrow, James W.; Henneberger, Roger C.; Granados, Eduardo E.

Key words
Drilling; forked well, multi-legged well, multilateral well, geothermal well productivity, well productivity enhancement
Conference
Geothermal Resources Council Transactions
Year
2007
Session
Drilling; Directional drilling; Feasibility studies
Language
English

Full text

Open the paper

Opens in a new tab

Abstract

This paper presents an analysis of the well productivity enhancement possible by drilling multi-legged (or “forked” or “multilateral”) wells in geothermal fields at temperatures in the 100 to 250°C range. A parameter, Productivity Enhancement Factor (“PEF”), is introduced to quantify productivity enhancement; it is defined as the ratio of the downhole productivity index of the multi-legged well to that of the original hole before the forked leg was added. Assuming the original hole to be vertical, it is shown that PEF rises sharply with deviation angle of the forked leg upto about 5 degrees; beyond this, PEF continues to increase with deviation angle albeit at a slower rate. A deviation angle of 25 to 30 degrees gives the highest percent increase in PEF per meter drilling of the forked leg (for a two-legged well) or legs (for a three-legged well). PEF is not significantly affected by reservoir temperature and declines rapidly with flow time for a few weeks before the decline rate stabilizes; PEF becomes nearly constant after a year or two of flow. The tighter the reservoir rock the more effective it is, in general, to enhance well productivity by drilling multi-legged wells. PEF of a two-legged well does not exceed a value of 2 unless the skin factor in the forked leg is less than in the original hole, in which case it can reach a value perhaps as high as 2.5. A three-legged well can provide up to 50% more PEF than a two-legged well, everything else being equal. Not only does a three-legged well pose a higher drilling risk, it is less effective in enhancing well productivity per unit drilling cost. Only where the original hole and the first forked leg both prove disappointing in productivity, drilling a second forked leg may be worthwhile.

Copyright 2007, Geothermal Resources Council. Readers who download papers from this site should honour the copyright of the original authors, and may not copy or distribute the work further without the permission of the original publisher.

Attend the 2026 Geothermal Rising Conference. Meeting details
You have opened 0 records today from 216.73.216.232 (216.73.216.232).
Viewed 22 September 2026, 9:27 am.