A Review of the Gunung Salak Geothermal Expansion Project

R. Soeparjadi, G. Horton, E. Bradley and P.E. Wendt

Location
Awibengkok, Indonesia; Java
Conference
New Zealand Geothermal Workshop
Year
1998
Session
Case Studies
Language
English

Full text

385KB, opens in a new tab

Abstract

In December 1997, Unocal Geothermal of Indonesia, partnership with PT Nusamba Geothermal, and PT PLN (Persero), completed the first private geothermal power buildoperate- transfer (BOT) project in Indonesia. Unocal installed three 55 and PLN installed one 55 Power Generation Facilities (PGF) to the total power generation at to 330 making the largest geothermal project in Indonesia. UGI also expanded the Resource Production Facilities (RPF) to increase steam delivery for six units. The project challenges included handling a liquiddominated resource, environmentally sensitive protected forest, difficult surface conditions, and coordinating on-going power generation operations and a three rig drilling program with new construction efforts. UnocalĂ­s power plants feature three identical Fuji turbines and generators, shell and tube surface condensers, concrete cross-flow air-induced cooling towers, and a hybrid gas removal system. Drilling, engineering, procurement and construction were accomplished within 28 months. Plant operators were locally hired and trained within the construction period, and are now operating all the project facilities. The plants have been generating at demand with up to 340 capacity since start-up.

Copyright 1998, University of Auckland. Readers who download papers from this site should honour the copyright of the original authors, and may not copy or distribute the work further without the permission of the original publisher.

You have opened 0 records today from 216.73.216.152 (216.73.216.152).
Viewed 24 September 2026, 2:05 am.