Injection Management at the Miravalles Geothermal Field
- Location
- Miravalles, Costa Rica
- Conference
- Stanford Geothermal Workshop
- Year
- 2004
- Session
- RESERVOIR
- Language
- English
Full text
247KB, opens in a new tab
Abstract
Electricity began to be produced at the Miravalles
geothermal field in early 1994. Since then, the
installed capacity has increased from 55 MWe to
142.5 MWe. A binary plant (15.5 MWe) will be
finishing its final tests by February 2004, increasing
the fieldÃs capacity to 158 MWe. The management
of injection in the field during nearly ten years of
exploitation is described in the following sections.
The most recent numerical simulation of the
Miravalles reservoir suggested changing the
distribution of injection (more to the west and less to
the south), in order to improve the performance of the
reservoir. These changes were implemented, and
their results are presented.
Copyright 2004, Stanford Geothermal Program. Readers who download papers from this site should honour the copyright of the original authors, and may not copy or distribute the work further without the permission of the original publisher.