Title: |
Pressure Response to Production and Injection at the Miravalles Geothermal Field |
Authors: |
Paul Moya, Sergio Castro |
Key Words: |
pressure response, injection, Miravalles Field |
Geo Location: |
Miravalles, Costa Rica |
Conference: |
Stanford Geothermal Workshop |
Year: |
2004 |
Session: |
FIELD STUDIES |
Language: |
English |
File Size: |
286KB |
View File: |
|
The Miravalles Geothermal Field has been producing
electric energy since March 1994. It has provided
steam for Unit 1 (55 MWe, installed 1994), a
wellhead unit (5 MWe, 1995), Unit 2 (55 MWe,
1998) and Unit 3 (27.5 MWe, 2000). Unit 5, a 15.5
MWe ìbottoming cycleî unit, is expected to
complete its final tests by February 2004, at which
point the total installed capacity in Miravalles will be
158 MWe. The behavior of reservoir pressure during
the period of exploitation is described in the
following sections. Over the first ten years of
exploitation, the field has successfully supplied the
steam needed to generate at the installed capacity.
Press the Back button in your browser, or search again.
Copyright 2004, Stanford Geothermal Program: Readers who download papers from this site should honor the copyright of the original authors and may not copy or distribute the work further without the permission of the original publisher.
Attend the nwxt Stanford Geothermal Workshop,
click here for details.