Two Phase Flow Gathering System at Coso Unit 1

Dietl, Bruno; Taylor, John; Martin, Bill

Key words
Production; USA; California; Inyo; Coso; Gathering System; NGG; Brine; Two Phase; Case Histories; Injection
Location
Coso, California
Conference
Geothermal Resources Council Transactions
Year
1989
Session
Two phase flow; Pipelines; Power plant design and operation
Language
English

Full text

Open the paper

Opens in a new tab

Abstract

The first geothermal Power Unit at Coso Hot Springs was built using a fast track design/construction concept. The time value of money to bring the project to full operation in the shortest time possible was an important consideration in making this decision. Of paramount importance was the commercial success of this first Coso project, in order to lay the groundwork of all future development at this location. California Energy Company, Inc., as the managing partner of the developer, selected the tam of Guy F. Atkinson Company, Mitsubishi Heavy Industries America, Inc. and Valley Engineers, Inc. to bring this project form conceptual design to power generation. This paper limits its scope to address the design and construction considerations of the two phase flow gathering system (first of its kind in the USA), the brine and noncondensable gas injection system and the steam vent facilities.

Copyright 1989, Geothermal Resources Council. Readers who download papers from this site should honour the copyright of the original authors, and may not copy or distribute the work further without the permission of the original publisher.