The Power Plant at Svartsengi, Development and Experience

Bjornsson, Gudmundur; Albertsson, Albert

Key words
Power Generation; Drilling; Production; Iceland; Svartsengi
Location
Svartsengi, Iceland
Conference
Geothermal Resources Council Transactions
Year
1985
Session
Power plant design and operation; Operations management; Fea
Language
English

Full text

Open the paper

Opens in a new tab

Abstract

The case history of design and construction of the power plant at the Svartsengi geothermal field is described in this paper. The construction took place several stages lasting from January 1976 to September 1981. The total installed power capacity is 125 MWt (thermal) and 8 MWe (electrical) in three turbogenerators. Total investment amounts to approximately $31 million (1984 US dollars). Development of design and construction is discussed and facts about investment and operating cost are accounted for. Development of geothermal wells is explained and construction and operation of new work over equipment for flowing geothermal wells are accounted. for.

Copyright 1985, Geothermal Resources Council. Readers who download papers from this site should honour the copyright of the original authors, and may not copy or distribute the work further without the permission of the original publisher.