Rehabilitation and Modernization Project for Unit 5 of Cerro Prieto Power Plant
- Key words
- Units modernization and rehabilitation, Residual energy utilization,Secondary steam utilization, Efficiency improvement,Cerro Prieto
- Location
- Cerro Prieto, Mexico
- Conference
- World Geothermal Congress
- Year
- 2005
- Session
- 13. Power Generation
- Language
- English
- Paper number
- 1318
Full text
42KB, opens in a new tab
Abstract
This project includes the increase of steam production in the field using the surplus energy from the separated water as the repowering of the Unit 5 rated 30 MW. This repowering considers the cooling tower substitution, turbine rehabilitation and non condensable gas extraction system.